Motorists in Glenwood Springs should expect several traffic impacts this week as city and state construction projects continue across the community. The most significant closures include temporary access restrictions to eastbound Interstate 70, nighttime lane closures on the Grand Avenue Bridge, ongoing work on Coach Miller Drive and 19th Street, and a two-month closure of the downtown parking garage.

City officials encourage drivers to plan ahead, allow extra travel time and follow posted detour signs through all construction zones.

Eastbound I-70 Access Closed Aug. 5–6

The most disruptive traffic change this week will affect drivers traveling east toward Denver.

On Wednesday, Aug. 5, and Thursday, Aug. 6, from 9 a.m. to 3 p.m., the CO 82 on-ramp to eastbound I-70 at Exit 116 (the main Glenwood Springs exit) will be closed while crews perform maintenance.

During the closure:

  • Eastbound I-70 traffic will be detoured via U.S. Highway 6 & 24 to the West Glenwood exit at Mile Point 114.
  • Westbound travel will not be affected.

Drivers heading toward Denver should expect additional travel time during the daytime closures.

Grand Avenue Bridge Lane Closure Tuesday Night

A rolling single-lane closure will take place on the Grand Avenue Bridge on Tuesday, Aug. 4, from 7 to 11 p.m. while crews install a banner.

Traffic will be maintained, but short delays are possible.

Downtown Parking Garage Closed Through Early October

Beginning Aug. 4, the city's 9th Street and Cooper Avenue parking garage is closed on both levels through Oct. 3.

The closure allows crews to complete:

  • Structural lintel and concrete crack repairs
  • Resurfacing of the upper parking deck
  • Drainage improvements

The city recommends:

  • Parking in the 7th Street public lot, which now has an improved pedestrian connection to downtown.
  • Using the free Ride Glenwood bus system, walking, biking or Ride Glenwood On-Demand whenever possible.

Coach Miller Drive Project Nearing Completion

Construction continues on the Coach Miller Drive improvement project, with crews entering the final paving phase.

From Aug. 5–7, drivers should expect single-lane closures on 14th Street between Grand Avenue and Pitkin Avenue while milling and paving operations are completed.

Additional project updates include:

  • Coach Miller Drive remains closed between Park Drive and 14th Street.
  • The Rio Grande Trail remains open.
  • Pedestrians and bicyclists should stay out of active construction areas.
  • Construction remains on schedule to finish before the start of the school year.

19th Street Remains Closed

Construction continues through August on the 19th Street utility and roadway improvement project.

19th Street remains fully closed between Grand Avenue and Blake Avenue.

The project includes:

  • New sewer infrastructure
  • Stormwater drainage improvements
  • Replacement curb and gutter
  • New asphalt pavement

Businesses remain open and can be reached via alternate access routes.

Drivers should use:

  • Hyland Park Drive from the north
  • 20th Street from the south

Parking lots between 19th and 20th streets remain open but are only accessible from 20th Street.

Shared Use Path Project Nearing Completion

Construction on the Highway 6 & 24 Shared Use Path between Donegan Road and Linden Street is entering its final stages.

Although crews are completing punch-list work, the path remains closed to pedestrians and bicyclists.

Travelers should continue using alternate routes while work wraps up.

Drivers may also encounter occasional lane closures near Traver Trail and Devereaux Road.

Additional Road and Event Closures

Residents should also be aware of several smaller traffic impacts around the city:

  • 5th Street between Laurel and Pine will close for two to three days in early August for pavement repairs.
  • Soccer Field Road is nearly complete, with only final striping remaining.
  • 7th Street between Colorado and Cooper avenues closes every Tuesday from 3 to 9 p.m. for the weekly Market on 7th.

Glenwood Canyon Construction Continues

Outside the city, the Colorado Department of Transportation continues bridge joint improvements along I-70 through Glenwood Canyon.

Work is taking place weekdays from 7 a.m. to 7 p.m. between Glenwood Springs and Dotsero, with intermittent lane closures throughout the 17-mile corridor.

The Glenwood Canyon Recreation Path remains fully open despite the highway work.

CDOT also continues planning for future renovations at the Bair Ranch, Grizzly Creek and No Name rest areas. Construction is expected to begin in 2027, with only one rest area closing at a time.

Private Development Progress

Several large private developments also continue moving forward in Glenwood Springs.

Construction is underway on the Silver Sage Development, a 40-unit duplex community near Four Mile and Airport roads, with some homes expected to be completed later this year.

Work also continues on the new Home2 Suites by Hilton at Glenwood Meadows. The 150-room extended-stay hotel is expected to remain under construction through 2026 and into the first half of 2027.

City Engineer Update Scheduled

Residents interested in learning more about current infrastructure projects can hear directly from City Engineer Ryan Gordon, who is scheduled to provide a construction update during the Glenwood Springs City Council meeting on Thursday, Aug. 6.

Share this post

Written by

Comments

AG nominee tells faith leaders he will take action to restrict abortion drug access
Acting U.S. Attorney General Todd Blanche, whose nomination advanced in the Senate on Tuesday, told faith leaders in a call on July 30 that he would take action to restrict mail-order access to abortion medication. (Photo by Shauneen Miranda/States Newsroom)

AG nominee tells faith leaders he will take action to restrict abortion drug access

By Colorado Newsline 2 min read
Feds to impose new cuts on lower Colorado River states amid climate-fueled megadrought
Glen Canyon Dam holds back the waters of Lake Powell near Page, Arizona, on Feb. 2, 2025. (Photo by Spenser Heaps for Utah News Dispatch)

Feds to impose new cuts on lower Colorado River states amid climate-fueled megadrought

By Colorado Newsline 3 min read
Fifty for 150: First peach trees planted on Western Slope of Colorado in 1882
A group of workers pack peaches at B.F. West’s Ranch in Palisade in 1907. (Courtesy of Denver Public Library Special Collections, MCC-1124)

Fifty for 150: First peach trees planted on Western Slope of Colorado in 1882

By Colorado Newsline 2 min read